Front WalkwayLots of good progress was made in June.

Outside, the brick walkway was installed. Gutters and rain collection barrels, too.

Inside, lots and lots of drywall sanding and painting. And interior trim and door jambs and windows. Beautiful stair treads. And even a start on installing kitchen cabinets!

Apologies for the slight “summer vacation” hiatus of the Construction Blog these past few weeks.

IF YOU HAVE PICTURES from any build days that you would like to contribute, please contact sudburyhabitat@gmail.com!

June 27 Build Day

The brick walkways have been completed, gutters installed, and rain collection barrels, too!

Click above for the photos…

June 3 Build Day

Another beautiful build day, and yet more progress.

Volunteers from Seagate and WPI were on site, and more drywalling (sanding and more mud) and exterior painting was done.

Work also began on the walkways — stone dust was placed and packed down, and the first few bricks were laid!