December 30 Build Day

Work on the soffits, some ice shield put down along edge of roof, work on firewall on second floor, some more interior wall framing on first floor.

Build Day 2008-12-30

December 27 Build Day

Sheathing of the walls is complete!!

Build Day - 2008-12-27

December 23 Build Day

Moved up to Tuesday due to Christmas Eve falling on Wednesday…

Build Day - 2008-12-23

December 20 Build Day

Major snowstorm the night before!! As a result, Saturday turned into a site clean up day for the hardy folks who could make it to the site.

Build Day - 2008-12-20

December 17 Build Day

We had almost made it to a completed roof, but the first significant snowfall just beat us. First order of business — shovel off the work area.

The framing of the rafters for the roof over the entrance way was finished.

Build Day - 2008-12-17

December 13 Build Day

Framing of the rafters for the roof over the entrance way — tricky stuff!

Click above for the photos…

And check out a slideshow video of the day’s work!

December 10 Build Day

Shingle delivery arrives and is unloaded. Stairs from first to second floor are completed — no more ladders required to reach the second floor!!

Some more first floor interior walls are built.

Walkway bricks (hand selected/picked by Habitat volunteers) are delivered.

Build Day - 2008-12-10

December 6 Build Day

Main roof sheathing is almost completed.

Build Day - 2008-12-06

December 3 Build Day

Installation of lots of roof trusses!

Build Day - 2008-12-03